LH to cut housing project lead times by 67 days using emergency bidding
LH announced a new fast-track procurement contract and commencement plan on November 19 to speed up housing supply. The plan follows the government's August 13 fast housing supply measures and aims to achieve early commencement. The new system manages procurement by working backward from the planned commencement date rather than managing by contract signing.
How the new system works
This approach strengthens advance coordination between procurement, contract, and review departments to eliminate procedural gaps. Emergency bidding will be used for urgent projects to prevent delays from failed bids, corrections, or re-announcements. The company's top priority is implementing the government's fast supply policy without fail to stabilize the housing market.
The new system reduces the time from procurement planning to commencement for comprehensive review contract awards over 30 billion won from 130 days to 63 days. This reduction of 67 days is achieved by skipping annual plan announcements, using emergency bidding, and shortening internal review periods. For intermediate contract awards between 10 billion won and 30 billion won, the period will be reduced from 105 days to 57 days.
For qualification review contracts under 10 billion won, the period will be reduced from 98 days to 43 days. The plan also applies to technical and general services, and the procurement of public housing design, construction, and supervision has been agreed upon. The company will create tangible housing supply results for the public by innovating the entire procurement, contract, and commencement process.
What is being reduced
The 67-day reduction for comprehensive review contract awards is achieved by skipping annual plan announcements, using emergency bidding, and shortening internal review periods.
The reduction for intermediate contract awards is 48 days, and the reduction for qualification review contracts is 55 days.
What is happening this year
LH has requested emergency bidding for 38 projects worth approximately 5.4 trillion won scheduled for commencement this year. The government announced the fast housing supply measures on August 13, 2026, which included plans to supply over 230,000 additional units in the Seoul metropolitan area under LH's leadership.
Glossary
- LH — LH announced a new fast-track procurement contract and commencement plan on November 19 to speed up housing supply. The plan follows the government's August 13 fast housing supply measures and aims to achieve early commencement.
- Seoul metropolitan area — The Seoul metropolitan area (Sudogwon; Korean: 수도권, [sʰu.do.k͈wʌ̹n]) or Gyeonggi region (경기 지방), is the metropolitan area of Seoul, Incheon, and Gyeonggi Province, located in north-western South Korea. Its population of 26 million (as of 2024)[1] is ranked as the fourth-largest metropolitan area in the world.
This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact
Comments 0